Last week, Gouldsboro received notice from the Maine Department of Transportation (MaineDOT) that it received a conditional award of $1,525,158 for its proposal to MaineDOT’s Maine Infrastructure Adaptation Fund (MIAF) to address a flooding problem at the stream crossing in the photo at the top of this post. Funding for this round of the MIAF program is supported by the National Oceanic and Atmospheric Administration Office for Coastal Management (NOAA OCM) through the Climate Resilience Regional Challenge (CRRC) awarded to the Maine Governor’s Office of Policy Innovation and the Future (GOPIF) in Fall 2024.
Gouldsboro’s proposal focused on a portion of Corea Road that frequently floods when the tide is high and strong winds blow from the south. In bigger storms, such as the one on January 10, 2024, the flooding cuts off the Francis Pound and Cranberry Point areas from emergency services, as shown below.


The award is conditional because, now that it has been reviewed and selected by MaineDOT for funding, it must go through a federal review to ensure that it is in compliance with federal guidelines established by NOAA OCM, including, but not limited to, the National Environmental Policy Act (NEPA) and related Environmental Compliance regulations. The federal review process may take several months.
This award results from work by the Town, its Coastal Resilience Committee (CRC), and Corea residents that began in August 2024. Here is a quick review of that work, including links to earlier posts on this site that provide more details.
- August 2024: Gouldsboro’s CRC met with 43 Corea residents and hydrologists and engineers from FB Environmental and Streamworks to hear about residents’ experiences in the January 2024 storms and to identify priorities for making the roads around Corea Harbor safer and more climate-resilient during storm events.
- November 2024: The CRC, accompanied by FB Environmental and Streamworks, met again with Corea residents to present several alternative design concepts to address the issues identified in the August meeting. The post describing this meeting includes pictures of the design alternatives and explains how a new alternative—replacing the culvert on Corea Road with a bridge—came from a fisherman working out of Corea Harbor.
- Spring and Summer 2025: Gouldsboro’s CRC worked with FB Environmental and Streamworks over the spring and summer to refine and focus the ideas and possibilities identified in the 2024 meetings. We learned that one of the areas that was damaged and flooded in January 2024 was eligible for mitigation funding through the Federal Emergency Management Agency (FEMA). Consequently, we focused on preparing a permit-ready design and associated documents for the stream crossing on Corea Road. This Fall 2025 post describes that work and our plans to seek funding for final design and construction.
- May 2026: Gouldsboro submitted its proposal for final bridge and road design and construction to MaineDOT.
Returning to Use of a Bridge
The CRC’s initial thinking was to raise the road and replace the 48″ culvert with a wide box culvert with an open bottom. However, as one participant noted at the November 2024 meeting, the stream crossing used to be a bridge. A landowner with property along the stream provided the photo below.

One letter supporting the Town’s proposal to MaineDOT described the advantages of returning to using a bridge.
I have lived with the realities of this crossing for many years, and I believe the current culvert has created both safety and environmental problems that will only worsen with time and stronger storms.
Before the old bridge was removed decades ago, the brook and stream crossing functioned much more naturally. The bottom of the brook maintained a relatively even and stable grade across the crossing. As a child, I spent a great deal of time there and saw firsthand how different the area was before the bridge was replaced with the current culvert.
One of the major issues with the culvert is that it was installed too high. Because of this, water backs up on the upstream side instead of flowing naturally through the system. During low tide after heavy rain events, water rushes out of the culvert with tremendous force, almost like a waterfall. Over the years, that concentrated flow has scoured out the brook bottom below the crossing, washing away sand and significantly altering the natural structure of the streambed.
In addition to the environmental damage, the roadway itself regularly floods during storms and full-moon tides. When water overtops the road, residents on Cranberry Point Road can effectively be cut off from emergency services. That is not simply inconvenient — it is a public safety concern.
Returning to a bridge-style crossing with a wider span would help restore a more natural flow of water, reduce the destructive force created by the current culvert system, and improve the longterm resilience of the road. It would also better accommodate tidal flow, storm surge, and runoff from intense weather events.
There used to be a bridge there for a reason, and I believe moving back toward that kind of design is both the right decision for the community and the surrounding environment.
The preliminary design in the now conditionally awarded proposal uses a modular steel bridge consisting of two pieces joined lengthwise along the middle of the road and elevates the road and bridge by 2 feet above its current height. If, in the future, Gouldsboro needs to raise the stream crossing again to accommodate sea level rise, it will be able to do so one lane at a time without building a temporary bypass road to handle traffic to the Francis Poud area and Cranberry Point while construction is underway.
What Comes Next
If Gouldsboro’s proposal passes federal review, the Town will enter into a contract with the State and can start permitting and design work sometime next spring. Final design, engineering, and permitting work will be complete by late summer or early fall of 2027, and the project will be ready to move into the bid phase by the end of 2027. Construction can only take place during in-stream and tidal work windows set by the Maine Department of Marine Resources and the U.S. Army Corps of Engineers. Given current work window regulations, construction will most likely begin in November 2028 and continue into 2029.